Uganda’s 600MW Karuma Hydropower Dam Project Close to Completion

Defects identified have been fixed in the country’s flagship power project.

By Chriselle Moraes on
15th June 2022

Uganda Electricity Generation Company Ltd (UEGCL) has detected and fixed defects in Uganda’s flagship power project, the Karuma Hydropower Dam, but is still likely to miss the June 2022 commissioning target date. UEGCL said it dealt with problems related to poor cabling and non-conformity with the standard of materials.

UEGCL CEO Harrison Mutikanga spoke at the routine inspection of the dam on 1 April 2022. He said progress on the dam was good so far, but the new commissioning plan by the contractor, Sinohydro Corporation, is still pending. "The biggest challenge was cabling con-conformances, and this has been corrected. New cables as well as new cable cabinets have been brought in and fixed including carrying out other modifications," Mutikanga said.

The Karuma Project is on the Nile River in Kiryandongo District in mid-northern Uganda, 110 kilometres downstream of Lake Kyogo and 270 kilometres from the capital Kampala. President Yoweri K. Museveni launched the construction work in August 2013. The original completion date was in December 2019, but was extended to June 2022, and is further subject to change.

The Karuma power station comprises a 20-metre high and 312-metre long roller compacted concrete (RCC) gravity dam, six 20-metre high and 29-metre wide water intake towers, six 7.7-metre diameter and up to 379-metre long concrete lined pressure shafts, and a 200-metre long, 21.3-metre wide and 53-metre high underground power house cavern housing six 100-megawatt vertical Francis turbines.

The plant reservoir is 35 kilometres long and covers 2,737 hectares. Gross reservoir volume is estimated at 79.87 million cubic metres. Design discharge for the plant will be 1,128 cubic metres per second and turbines will operate under a gross head of 70 metres, at a speed of 150 rotations per minute. 

On completion, the hydropower facility will have a power generation capacity of 600 megawatts.

Generated power will be evacuated through a 200-metre-long, 18-metre-wide, and 14.4-metre-high transformer cavern which will house six 11-kilovolt/400-kilovolt (kV) step-up transformers and will be connected to the powerhouse through a 40-metre-long duct tunnel.

The power station will also have two 314-metre-long, 21.5-metre-wide and 50-metre-high restricted orifice type tail race surge chambers. The water will be sent back from here to the river through two 12.9-metre diameter horseshoe-shaped tail race tunnels of approx. 8.6 kilometres long. 

The Karuma-Kawanda line, Karuma-Olwiyo line and the Karuma-Lira transmission line will feed power to the national grid. Uganda Electricity Transmission Company (UETCL) will construct three new substations at Karuma, Kawanda and Olwiyo.

The project costs US$1.7 billion with the Ugandan government contributing 15% and EXIM Bank (Loan China) covering 85%. The owner's engineer for the project is AFRY Switzerland Ltd.  Electricity generated will contribute to the national power grid with the surplus exported to neighbouring South Sudan.

Proscovia Njuki, chairperson of the Board of Directors at UEGCL praised the level of contractor commitment towards closing the non-conformities identified and expressed hope for a 2022 commissioning date. 

“The corrosions are being addressed with a good paint. We are really happy as a Board that the things that were of concern as we move towards the commissioning have been addressed and we should be able to commission soon," she said.

Top Photo: Karuma Hydropower Dam (uegcl.com)

Add a comment

ConstructAfrica welcomes lively debate, but will not publish comments that are threatening, libellous or abusive.

Plain text

  • You can align images (data-align="center"), but also videos, blockquotes, and so on.
  • You can caption images (data-caption="Text"), but also videos, blockquotes, and so on.
  • Web page addresses and email addresses turn into links automatically.
  • Allowed HTML tags: <a href hreflang> <em> <strong> <cite> <blockquote cite> <code> <ul type> <ol type start> <li> <dl> <dt> <dd> <h2 id> <h3 id> <h4 id> <h5 id> <h6 id> <img src alt data-entity-type data-entity-uuid data-align data-caption>